Campus Center Construction Impacts - September 2020

General:

*Surface Lot 2 and Student Center parking deck remain open for public use.

*Heavy construction traffic in this sector of campus.

*Normal working hours are Monday - Saturday 6:00 AM – 5:30 PM.

Arts Plaza Exterior Work:

*Pavers and sidewalk in front and around the Ferst Center Arts Plaza is complete. 

*Fencing has been modified to open up Ferst Center front doors and the connecting pathway around the Ferst Center for the Arts.

Phase II Building Construction:

*Construction fencing is installed around perimeter of the site.  Wayfinding signage is installed. 

* Demolition of the Stamps Commons building is ongoing, the above grade structure has been demolished with only the post office and foundations remaining. 

* Pedestrians to be aware of high truck traffic leaving the loading dock of the existing Wenn building as debris is hauled off site.

* Interior demolition of the Wenn Student is underway.

 

 

 

 

 

Related Links

Related Media

Click on image(s) to view larger version(s)

  • Campus Center Construction Impacts - September 2020

    Campus Center Construction Impacts - September 2020

For More Information Contact

Nicolas Palfrey

Capital Project Manager

Georgia Institute of Technology | Facilities Design & Construction