Construction Notices

Keeping our campus running smoothly is our number one priority. If you have questions regarding the below notices and detours, please contact Facilities Management: Design and Construction.

 

Construction Activity Between Student Center and Smithgall Continues Into Spring

The alternate pathway in place around the Smithgall Student Services building will remain in place as construction work between the Smithgall and the Student Center site stretches into the new semester. The necessary work, once hoped to last only a few weeks, has proved more complex and will require more time to complete and restore the pathway. 

Campus Center Renovations Continue December 2021 through January 2022

While the fence line has been static for some time, this notice documents a brief change to execute hardscape work from Ferst Plaza down to the parking lot.  The work has been scheduled to avoid events in the Ferst Theater and at a time when campus is fairly quiet to minimize the disruption. 

General:

*Student Center Lot 2 and Student Center parking deck remain open for public use.

*Normal working hours are Monday - Saturday 6:00 AM – 6:00 PM.

Phase II Student Center Construction - Hardscape:

McMillan Street Closure December 20

This notification is to advise of a road closure at McMillan St, NW and Turner Place, NW in the West Campus Sector on Monday, December 20th from 7 a.m. to noon.  To change out a transformer,  a crane will be set up at the intersection so no thru-traffic will be possible. Cones and signage will be placed at Ferst Drive onto 6th Street. 

There will be some re-routing of pedestrian foot traffic to keep the public from entering the Work Zone of the Crane.

City of Atlanta Water Main Installation Impacts Techwood Drive December 20 - 23

December 20 through Dec. 23, the City of Atlanta will complete the service connections to finalize the 12-inch water main installation that occurred in October along Techwood Drive between North Avenue and 3rd Street/Bobby Dodd Way (adjacent to Bobby Dodd Stadium). 

The City of Atlanta will also mobilize the week of January 3 for 2-3 weeks to complete the final connection of the new main and disconnection of the old.

Paper Tricentennial Building Front Driveway Entrance Closed Oct. 6 - Oct. 15

The Paper-Tricentennial Building's front driveway entrance will be closed from October 6 - October 15 for driveway improvements.  During this period, all automotive and emergency access will utilize the rear entrance as shown on the map. This route has been proven to maintain 14'+ and accommodate a fire truck. The temporary closure is permitted by the Georgia Tech Fire Safety Office.

 

 

Boiler Transfer from A. French Building to Bradley Building 9/9 and 9/10

A large equipment moving operation will take place in the vicinity of A. French and Bradley/Administration Building on the Hill 09/09 and 09/10 (7 a.m. to 10 a.m.).  The operation will involve the movement of two (2) large boilers from the loading dock at A. French to the basement of Bradley Building with the use of a forklift.  Pedestrians are requested to STAY ALERT AND FOLLOW ALL SAFETY COMMANDS BY THE CONTRACTOR while navigating through the work zone from 7 a.m. to 10 a.m. on 09/09 and 09/10.

The schedule is as follows for each day:

City of Atlanta Water Main Installation Impacts Techwood Drive Intermittently Through October

The City of Atlanta is installing a 12-inch water main along Techwood Drive between North Avenue and 3rd Street/Bobby Dodd Way (adjacent to Bobby Dodd Stadium). The work has paused for the beginning of fall semester but will now resume intermittently through October. During installation, the northbound lane will be closed during normal business hours (approximately 9 a.m. - 4 p.m.) Monday through Friday. The southbound lane will be used to maintain two-way traffic, with traffic controllers, during working hours. Both lanes of Techwood Drive will be open each night.