The Planning, Design and Construction department is responsible for providing architectural and engineering design, construction management and contracting services for large and small campus projects. These projects are usually accomplished by outside contractors and managed by our in-house project managers.

NOTICE (5/24/23):

Due to lingering pandemic-related worldwide supply chain issues, many projects are experiencing longer than anticipated schedules as well as increased costs. Please be aware that these issues may impact your project's budget and final completion date. Your assigned Georgia Tech Design & Construction Project Manager will keep you informed of critical delays and cost implications as your project develops. We thank you for your patience and understanding.  Below is a list of materials and products that we know are currently experiencing supply chain delays.

Construction material delays:

Steel 16 weeks
Metal decking 24-28 weeks
Roof insulation 32-36 weeks
AHUs 45-52 weeks
Electrical switch gear 52 weeks
Panels 18 months
Transformers 24 months
UPS 26 weeks
Elevators 30-36 weeks
Brick pavers 72 weeks
Laser curtain 12 weeks
Lab casework 20 weeks
Terra cotta tile 72 weeks
Furniture 8-16 weeks after PO issued

AV and network gear delays:

Netgear switches (M4250 and M4300) 8-12 weeks
HP/Dell Computers  
AMX N8002 SVSI controllers (limited stock)  
AMX SVSI audio transceivers (2023)  
AMX NX-3200 control processors (limited stock)  
AMX NX-4200 control processors (limited stock)  
Extron IN1608xi IPCP MA70 switcher 72-96 weeks
Extron 5" TPs 72-96 weeks

 