The Planning, Design and Construction department is responsible for providing architectural and engineering design, construction management and contracting services for large and small campus projects. These projects are usually accomplished by outside contractors and managed by our in-house project managers.
NOTICE (5/24/23):
Due to lingering pandemic-related worldwide supply chain issues, many projects are experiencing longer than anticipated schedules as well as increased costs. Please be aware that these issues may impact your project's budget and final completion date. Your assigned Georgia Tech Design & Construction Project Manager will keep you informed of critical delays and cost implications as your project develops. We thank you for your patience and understanding. Below is a list of materials and products that we know are currently experiencing supply chain delays.
Construction material delays:
Steel | 16 weeks |
Metal decking | 24-28 weeks |
Roof insulation | 32-36 weeks |
AHUs | 45-52 weeks |
Electrical switch gear | 52 weeks |
Panels | 18 months |
Transformers | 24 months |
UPS | 26 weeks |
Elevators | 30-36 weeks |
Brick pavers | 72 weeks |
Laser curtain | 12 weeks |
Lab casework | 20 weeks |
Terra cotta tile | 72 weeks |
Furniture | 8-16 weeks after PO issued |
AV and network gear delays:
Netgear switches (M4250 and M4300) | 8-12 weeks |
HP/Dell Computers | |
AMX N8002 SVSI controllers (limited stock) | |
AMX SVSI audio transceivers (2023) | |
AMX NX-3200 control processors (limited stock) | |
AMX NX-4200 control processors (limited stock) | |
Extron IN1608xi IPCP MA70 switcher | 72-96 weeks |
Extron 5" TPs | 72-96 weeks |