As part of the East Campus Streetscape project, milling and paving will include Centennial Park Drive this week.

Milling and paving operations for southbound lanes on Centennial Park Drive from North Avenue to Merrits Ave will be occur Tuesday, Sept. 10. The northbound lanes will occur Wednesday, Sept. 11. Attached please find the detour traffic patterns around the closed lanes while construction is in progress. The affected lanes will be closed daily from 9 a.m. to 5 p.m. The project should be complete by Thursday, Sept. 12, barring any weather delays. 