As the Baptist Collegiate Ministry prepares to construct a new building on its current footprint, initial utility work begins.

In preparation for the construction of a new building for the Baptist Collegiate Ministry (BCM), the installation of temporary utility poles-will begin along the west side of Techwood Drive on Mon. Aug. 25. Please note this is not a Georgia Tech-owned construction project. 

Georgia Power targets an anticipated completion date of September 5th. Below is a tentative schedule of activities during this period:

  • Week of August 25: Installation of new poles in preparation for underground work
  • Week of September 1: Boring of conduit and installation of underground cable
  • By September 5: Energizing underground cable and removal of overhead lines

Once the vendors involved are finished with their work, Georgia Power will return to remove the temporary utility poles.   

Further details to come as they are received. Thank you for your understanding and patience as this project progresses.