Utility infrastructure work will be ongoing during this timeframe.
Sep 05, 2025
Georgia Power will continue work along Techwood Drive for the Baptist Campus Ministry project (not a Georgia Tech project) over the next two weeks. They anticipate minimal impact on pedestrian and vehicular traffic flow. They will have traffic control personnel on-site to manage and maintain the flow and ensure smooth movement. They are coordinating efforts with GTPD. The work they will be doing and timing:
- Week of September 8: Installation of road crossings for underground cable
- Week of September 15: Energizing underground cable and removal of overhead lines
Thank you for your patience as this project progresses.