Submitted by cl220 on
Type of Review
Initial
Plan Type
Construction
Reviewer
Larry Labbe
Disposition
Approved
Estimated Completion Date
Actual Completion Date
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
AiM Project Number
180-2015
Project Manager
Gerald Shumake
Budget
$1000000