Type of Review
Initial
Occupancy Type
Business
Plan Type
Construction
Reviewer
Larry Labbe
Disposition
Consultation Complete
Estimated Completion Date
Actual Completion Date
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Project Manager
Lindsey Cottingham
Budget
$23000000
Department
Review Letter
615
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No