Type of Review
Revision
Occupancy Type
Business
Use Type
Lab
Plan Type
Construction
Reviewer
Jake LeJeune
Disposition
Approved
Estimated Completion Date
Actual Completion Date
Permit Number
2018-CP-235
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0263-2018
Project Manager
Ngugi Mathu
Budget
$300000
Construction Manager
Mitchell Shelton
847
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No