Type of Review
Revision
Occupancy Type
Business
Use Type
Office
Classroom/Instructional
Plan Type
Construction
Reviewer
Jerry Marrison
Disposition
Approved with Additional Requirements
Estimated Completion Date
Actual Completion Date
Permit Number
2019-CP-155
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0421-2018
Project Manager
Mitchell Shelton
Budget
$999999
Construction Manager
Mitchell Shelton
Department
Review Letter
1195
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No