Type of Review
Initial
Occupancy Type
Other
Use Type
Other
Plan Type
Construction
Reviewer
Jerry Marrison
Disposition
Approved with Additional Requirements
Estimated Completion Date
Actual Completion Date
Permit Number
2019-CP-190
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
AiM Project Number
0264-2017
Project Manager
Brad Morris
Budget
$1300000
Construction Manager
Brad Morris
1230
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No