Type of Review
Initial
Occupancy Type
Assembly
Use Type
Classroom/Instructional
Plan Type
Construction
Reviewer
Jerry Marrison
Disposition
Approved with Additional Requirements
Estimated Completion Date
Actual Completion Date
Permit Number
2019-CP-191
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0350-2019
Project Manager
Amber Chellis-Omedo
Budget
$150000
Construction Manager
Fenella Bryant
1231
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No