Type of Review
Initial
Occupancy Type
Business
Use Type
Other
Plan Type
Logistics - Crane Plan
Reviewer
Jake LeJeune
Disposition
Approved with Additional Requirements
Estimated Completion Date
Actual Completion Date
Permit Number
2019-CPL-208
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0914-2019
Project Manager
Federico Del Risco
Budget
$10688
Construction Manager
Federico Del Risco
Department
Review Letter
1248
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No