Type of Review
Initial
Occupancy Type
Business
Use Type
Lab
Plan Type
Construction
Reviewer
Jake LeJeune
Disposition
Declined
Estimated Completion Date
Actual Completion Date
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0398-2019
Project Manager
Maria Ceballos
Budget
$250000
Construction Manager
Cristina Fannin
1279
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No