Type of Review
Initial
Occupancy Type
Dormitory
Use Type
Dormitory
Plan Type
Site Plan Only
Reviewer
Jake LeJeune
Disposition
Approved
Estimated Completion Date
Actual Completion Date
Permit Number
2020-SP-009
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0443-2019
Project Manager
Daniel Powell
Budget
$200000
Construction Manager
Daniel Powell
Department
1412
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No