Type of Review
Initial
Occupancy Type
Business
Use Type
Office
Plan Type
Construction
Reviewer
Jake LeJeune
Disposition
Declined
Estimated Completion Date
Actual Completion Date
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
0334-2020
Project Manager
Carla Barbour
Budget
$900000
Construction Manager
Carla Barbour
Department
Review Letter
1523
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No