Type of Review
Initial
Occupancy Type
Assembly
Use Type
Stadium/Grandstand
Plan Type
Temporary Structure
Reviewer
Jerry Marrison
Disposition
Approved
Estimated Completion Date
Actual Completion Date
Permit Number
2021-TS-027
Fast Track?
No
Is there a Facilities Management Project Request # for this project?
No
Building
AiM Project Number
2020-0359
Project Manager
Lindsey Cottingham
Budget
$10000000
Construction Manager
Lindsey Cottingham
Department
Review Letter
1749
Date that Permit will be Required
Date that Construction will Start
Letter to Proceed?
No