The installation of chilled water piping will begin Monday, June 14 and is expected to continue through Thursday, August 17.  Due to weather delays and changes to the installation of thermal insulation the project may run through 8/23.

The Paper Tricentennial Chilled Water Project  

The installation of chilled water piping will begin Monday, June 14 and is expected to continue through Thursday, August 17.  Due to changes in the thermal insulation required for the piping, work may continue through August 23. Daily work hours are between 7am and 3:30 pm. Construction activities include saw cutting, removal of asphalt and excavation work for the installation of new chilled water piping. 

On Friday June 11, the contractor will restrict access to (8) parking spaces on 9th Street (highlighted in green). The plan is subject to change in case of inclement weather.

Thank you for your patience during this campus improvement.