In the month of November 2019, Phase I work including construction of the Exhibition Hall, Pavilion and Café buildings will continue for the Campus Center project.
General:
*Construction traffic in this sector of campus.
*Normal working hours 6:00 AM – 5:30 PM.
Phase I Building Construction (within project fence line):
*Pre- Engineered Metal Buildings and roofing for the Café and Pavilion buildings will be erected.
*Exterior metal framing, sheathing, and waterproofing at the Exhibition Hall will continue.
*Roofing at Exhibition Hall will be substantially complete.
*Exhibition Hall masonry and window systems installation will begin.
*Overhead mechanical, electrical, and plumbing systems at the Exhibition Hall will be installed.
*Interior metal framing walls and door frames will be installed at Exhibition Hall.
Phase I Utilities:
*Storm, sanitary sewer, and power ductbank will be installed north of the Student Center Parking Garage 9/6/2019 – 12/20/2019. Work should pass Smithgall 11/15
*Fencing will remain in place to provide barriers between construction activities and the campus.
*Signage will remain in placed around perimeter of fencing to direct pedestrian traffic.
*Pedestrian pathways approaching Ferst Center from ISYE lawn have been installed to divert walkways around construction.
*Way finding signage has been placed around this part of campus to provide alternate routes.
*ADA pathways will be maintained from the parking lot in front of Student Services to Ferst Center for the Arts.